Q: What is a ‘World Class OEE’? Is 85% OEE World Class?
Dennis McCarthy • When I say that Effectiveness is a measure of how well you did what you planned to do I want to be sure that the measure excludes time when you didn’t expect to run the machine. For sure the goal is to maximise effectiveness.
85% World Class
The “85% OEE is world class” comes from a TPM book written by Mr Nakajima who set out what he rightly considered to be world class in a machine shop in 1970’s. This was based on zero breakdowns, 10% of time on set ups, 5% performance loss due speed losses and 1% quality defects. That is still pretty impressive for a machine shop but even a poor process plant would run much higher OEE.
A more robust measure of world class is the OEE improvement trend. From a standing start a 50% increase in OEE over 3 years is a common achievement which often exceeds what they thought of as 100%,
The key for me is to keep it simple, aim for 80% of the answers with 20% of the data and use the measure to drive the improvement trend. As you approach 100% you will also improve process capability and can increase the precision of your measure to raise the bar further. OBE (Overall Batch Effectiveness) has a higher data capture overhead so only use it if you need to.
See also:
Can 85% OEE be NOT world Class?
List with expected world class OEE’s
Compare OEE when defined according the OEE Industry Standard
OEE Definitions
OEE Questions
Answer still not found?
If you checked all the sections in the Academy, yet still not found the answer to your question, ask it here.
To help you best, please be as specific as possible and please understand:
We do not want to reply to anonymous questions.