OEE Academy button
2. TEEP: What is the difference between OEE – OOE – TEEP?

Q: What is the difference between the OEE, OOE and TEEP measurements? 

Overall Equipment Effectiveness measures a machine’s availability, performance and quality in order to visually display all the losses that occur on this machine. So how do OOE and TEEP measurements differ from OEE?

Arno Koch •  The three measures are all visualising effectiveness losses.

The only difference between OEE, OOE and TEEP is the ‘maximum time’ that is used in each calculation.

In other words, the only changing variable between these three calculations is the maximum time that is available for a machine to run. They all take availability, performance and quality into account.

What is TEEP?

Total Effective Equipment Performance Considers maximum time to be All Available Time – that is 24 hours, 365 days a year.

TEEP is the ratio between producing 24/7 at theoretical maximum speed with no quality defects versus the actual good output during this time.

What is OOE?

Overall Operations Effectiveness takes unscheduled time into account, looking at Total Operations Time as a maximum.

OOE is the ratio between the actually produced good products versus the theoretical maximum output during all scheduled shift-time, including the unscheduled shift-time.

What is OEE?

Overall Equipment Effectiveness looks at the Potential Production time as a maximum, without calculating time that has been unscheduled.

OEE is the ratio between the actually produced good products versus the theoretical maximum output during all scheduled shift-time minus the unscheduled shift-time.

OEE – OEE – TEEP in a visual loss diagram

oee-ooe-teep diagram

Introduction: what is the basis for the OEE-OOE-TEEP KPI’s ?

In the ideal world, manufacturing equipment would be adding value all the time, at theoretical maximum speed, in precisely the desired quality.
So, if we want to know why our equipment is not ideal, there are 4 questions to be answered:

  1. Was the machine scheduled to run or not? The time it is scheduled to perform is also referred to as shift-time or loading time.
  2. When the machine was scheduled to produce, for what reasons was it not running? What was stopping the conversion process?
  3. When it was running, how come it was not running at theoretical maximum speed? What was reducing its speed?
  4. In the produced output; what quality defects occurred?

Availability within OEE ánd OEE/TEEP: Was the machine having output or not?

A machine is scheduled (‘Loaded’) in order to produce. When the machine is scheduled, we measure: “Was it having output, regardless the speed and the quality?”.
The relation between the time the machine was having output and the time it could have produced output (here is the difference in the 3 KPI’s)  is called

Availability rate: The percentage of time the machine was available, was able to produce output.

Performance: Was the machine running at it’s theoretical maximum speed?

Whenever the machine is running, thus really produces output, we determine how much, or how fast, the output was produced.

The ratio between the theoretical quantity of output while running, versus what actually came out, is the Performance rate.

Quality: Was all output according to the specifications?

From everything that came out, it is determined whether it was meeting the quality as expected. Was the output within the specification?

The ratio between the total actually produced output and the good output is called the Quality rate.

There are several KPI’s possible around those three rates. The main difference is the time-frame that is been considered while looking at availability.

In the end they all those KPI’s want to know: How much good product came out versus how much could it have been produced? And here is the crux: it all depends on what time frame is considered.
If we look at a years’ production; is this now based on 365 days of 24 hrs? Or is it only the time of all the shifts we would have scheduled? Or only the actually scheduled shifts? Or do we only consider the time we planned the machine to run within the scheduled shifts?

The OEE-OOE-TEEP KPI cascade

Let’s break it down to the core.

Total Effective Equipment Performance (TEEP)

If we want to know the real utilization, the real effectiveness of our equipment, we look at the amount of good product produced versus what could have been produced if there would have been no restraint at all.

This is what TEEP does. It takes 24hrs of 365 days a year as potential production time.
A well defined TEEP (and this also applies to OOE and OEE) takes the theoretical output as a maximum for performance and OTIF (so within specification AND on time) as a quality limit.

How is TEEP being calculated

TEEP calculates availability as a ratio between the TOTAL calendar-time during the measurement versus the time the machine was actually having output in that period.

So in a 1-shift operation of 40 Hrs during an 168 week, the availability can be theoretically no more than 40/168= 23% (assuming OEE=100%). TEEP now shows clearly that the equipment is sleeping at least 77% of its life time due to the fact it is not scheduled to produce. In this example TEEP = Loading Rate.

So one could also say:

TEEP = Loading Rate x Availability Rate x Performance Rate x Quality rate   …or

TEEP = Loading Rate x OEE

Overall Operations Effectiveness (OOE)

For those working in the daily operation, TEEP uses a time-frame that is ‘too wide’. The operations management is interested in the effectiveness of the equipment during operations time. So the first filter to apply is to take out all the time that the equipment was not scheduled anyway.
In other words:

OOE uses all regular shift time as the time-frame.

Overall Equipment Effectiveness (OEE)

This is the KPI for the shopfloor-team.

OEE relates the actual good output versus the ultimate potential good-output while the machine was scheduled to run. (So during the actually scheduled shift time).

Example

What if we have a line that runs one shift (8 hrs) and there is a production plan is for that time; what happens with the other two shifts? In theory the line is available to run 3 shifts, but its been used for just one shift.

  • There is ONE shift scheduled: The OEE will be measured over that shift. Non scheduled time (two shift that day, plus the missing shifts in the weekend) are not included.
  • There is no unscheduled time (time taken out of the scheduled time) so the OOE equals the OEE.
  • The TEEP will be calculated over the TOTAL time, so the scheduled plus the not scheduled shift: it will be fundamentally lower.

Proper OEE Software visualizes ALL effectiveness LOSSES on your machine, since that is the area where you will find your improvement potential. Even when losses are excluded from the OEE definition; they should become visible in the analysis!

 

 

See also: 

Answer still not found?

If you checked all the sections in the Academy, yet still not found the answer to your question, ask it here.
To help you best, please be as specific as possible and please understand:
We do not want to reply to anonymous questions.